The actions, identified by code PI 22-23/1790, have made it possible to eliminate architectural barriers and improve the rainwater collection service in the municipality.
The contract for the works was awarded to the company DUCAl URBANA, S.L. for a total budget of €39,776.03, plus €8,352.97 for 21% VAT.
The site survey and commencement of works report was signed on January 7, 2026, initiating the project. The material reception of the investment took place on March 30, 2026, with the signing of the corresponding report.