“"With the award to BECSA, we are entering the final phase of a complex engineering work of vital importance for the urbanistic future of Burriana for generations to come. We are ensuring the continuity of a historic investment that will not only solve the structural drainage and flood problems in our municipality but also provide us with a modern, resilient, and sustainable system capable of utilizing rainwater for the irrigation of public spaces."
Burriana awards final phase of Gran Colector for 1.02 million euros
The project, to be completed in 2027 with a total investment of 4.5 million, will improve stormwater management and flood prevention.
By Pau Ferrer Castelló
••2 min read
IA
Gran Colector works in Burriana with underground piping.
The Burriana City Council has awarded BECSA the fourth and final phase of the Gran Colector, with a budget of 1,026,574.66 euros. Work will begin in mid-September and will complete a priority infrastructure for stormwater management.
The intervention, with a seven-month execution period, will focus on connecting large-diameter pipes from the roundabout of the indoor swimming pool to Camí Fondo and Plaça de la Generalitat Valenciana. This action will improve safety against torrential rain episodes in sensitive areas such as Escorredor and Finello.
The project includes the construction of a large manhole on Carretera del Puerto, from which a 1,800 mm diameter collector will run to Plaça de la Generalitat. A new network will also be created on Avinguda Jaume I, culminating in a storm tank near Camí Fondo. Inlets will be installed at critical points and Sustainable Drainage Systems (SuDS) will be incorporated.
With this award, the Gran Colector enters its final stage. This infrastructure, which has involved a historic investment of over 4.5 million euros by 2027, diverts rainwater at a depth of four meters to the Anna River. The project also includes water reuse for irrigation of green areas and leisure gardens through storm tanks.
The infrastructure features two storm tanks, one in Sant Blai and another larger one near Avinguda Cardenal Tarancon, which increase Burriana's drainage capacity. The goal is to ensure citizen safety and reduce the impact of torrential rains, especially in the maritime zone.
Based on information from the official source: Ajuntament de Burriana (14/08/2026)